Free Cheat-test Samples and Demo Questions Download
Adobe exams Adobe
Apple exams Apple
Avaya exams Avaya
Check Point exams Check Point
Cisco exams Cisco
Citrix exams Citrix
CIW exams CIW
CompTIA exams CompTIA
CWNP exams CWNP
EC-Council exams EC-Council
EMC exams EMC
Exin exams Exin
Fortinet exams Fortinet
GIAC exams GIAC
Hitachi exams Hitachi
HP exams HP
IBM exams IBM
Isaca exams Isaca
ISC exams ISC
ISEB exams ISEB
Juniper exams Juniper
LPI exams LPI
McAfee exams McAfee
Microsoft exams Microsoft
Oracle exams Oracle
PMI exams PMI
Riverbed exams Riverbed
SNIA exams SAP
Sun exams SAS
Symantec exams Symantec
VMware exams VMware
All certification exams

Microsoft MB5-625 Exam - Cheat-Test.com

Free MB5-625 Sample Questions:

Q: 1
Registrations of projects must always be indicated by...
A. project number and nothing else
B. project number, CT and head. CT
C. project number and CT
D. time registration
Answer: C

Q: 2
The "Project is posted in finance" parameter shall be set to yes, if ...
A. the inventory table is used
B. costs posted in the project journal must be posted in G/L
C. invoicing is done from the project table
D. the salary module is used
Answer: B

Q: 3
If you use the invoicing principle, when should you allocate 100%?
A. At the end of each financial year
B. When the project has been fully invoiced
C. At the end of the year in which the project has been fully invoiced
D. Never
Answer: B

Q: 4
Which employees can be registered in project postings?
A. All employees who have been created in the employee table
B. Only the employees appearing in the "Sales rep." field
C. All employees who are registered with usernames in C5
D. This functionality is not possible
Answer: A

Q: 5
If costs are budgeted to a project with a parent project, how are these costs registered to the main project?
A. These costs must be manually stated for the main project under the tab "Head. CTs" on all project levels
B. In the case of several project levels, the head. CTs are only updated automatically on the level just above the sub‐project
C. In the case of several project levels, the head. CTs are updated on all levels
D. In the case of several project levels, the head. CTs are only updated at the lowest level
Answer: C